Eastbound Lanes of Southwest Third Street to Remain Closed Through November

Eastbound Lanes of Southwest Third Street to Remain Closed Through November

The eastbound lanes of Southwest Third Street from Southwest Pryor Road to Southwest Murray Road are now expected to remain closed through November 2020, while one westbound lane of Southwest Third Street will remain open. Southwest Third Street will then reopen to two-way traffic as the contractor works on the remaining lanes. This work is necessary as part of the Third Street Improvements project.

Private utility relocation issues have had a significant impact on the contractor’s schedule. The new completion date for the project is late spring 2021. Depending on the weather and the project’s progress, the contractor may have to stop work over the winter months. Should a winter shutdown occur, the contractor is expected to do the following: restore two-way traffic on Southwest Third Street; positive drainage to ensure no standing water; no obstacles, such as street plates or raised manhole lids, for snowplows; north/south access across Southwest Third Street for Southwest Murray Road traffic; and access maintained for all property owners.

Construction is weather dependent, and schedules are subject to change. A project update will be provided as winter approaches.

For more information about the Third Street Improvements project, contact Public Works at 969-1800 or publicworks@cityofls.net.

Print

Latest News

Community Notification: Flood Hazard Revisions Along Cedar Creek

Community Notification: Flood Hazard Revisions Along Cedar Creek

The City of Lee’s Summit, Missouri, Public Works Department in accordance with National Flood Insurance Program regulation 65.7(b)(1), hereby gives notice of the City of Lee’s Summit’s intent to revise the flood hazard information, generally located upstream and downstream of SW Ward Road along Cedar Creek. The flood hazard revisions are being proposed as part of Letter of Map Revision (LOMR, Case No. 22-07-0797P) for a completed construction...
Surface Seal Work Set to Begin on SE 2nd Street

Surface Seal Work Set to Begin on SE 2nd Street

Update: The contractor working on SE 2nd Street had an equipment failure earlier today, Tuesday, Nov. 1, and stopped work; however, work is tentatively expected to take place again from 9 a.m. – 4 p.m. tomorrow, Wed., Nov. 2. In order to complete surface sealing along SE 2nd Street at intersections, there will be short-term closures of Jefferson, Market, SE Main, Douglas and Green crossing SE 2nd Street. Eastbound and westbound traffic will be maintained...
Section of SW Jefferson Street Also Closed for SW 3rd Street Utility Work

Section of SW Jefferson Street Also Closed for SW 3rd Street Utility Work

Section of SW Jefferson Street Also Closed for SW 3rd Street Utility Work
Update: Phase two of the SW 3rd Street utility work is now expected to start on Mon., Oct. 17, with the closure of both eastbound and westbound through traffic on SW 3rd Street from SW Blue Parkway to SW Jefferson Street. The section of SW Jefferson Street from SW 3rd Street to SW 2nd Street is expected to be back open by noon on Mon., Oct. 17. During phase one of the utility work on SW 3rd Street which started today, a section of SW Jefferson Street from SW...
Section of SW 3rd Street Set to Close to Through Traffic Oct. 10

Section of SW 3rd Street Set to Close to Through Traffic Oct. 10

Section of SW 3rd Street Set to Close to Through Traffic Oct. 10
Update 2/28/23: Both eastbound and westbound lanes of SW 3rd Street from SW Blue Parkway to SW Jefferson Street are now open to through traffic. Utility work continues primarily in the center/middle lane as the crew is still proofing the pipe and pulling cables through the duct bank. This work is anticipated to be complete in two weeks, weather permitting. A section of SW 3rd Street from SW Blue Parkway to SW Jefferson Street is set to close to through...
Volunteers Needed for Stream Team Cleanup

Volunteers Needed for Stream Team Cleanup

Volunteers Needed for Stream Team Cleanup
The City of Lee’s Summit is looking for volunteers to participate in a Stream Team Cleanup on October 8. Volunteers will help remove litter and debris from a Prairie Lee tributary from 10 a.m. - noon at Upper Banner Park, 520 NE Noeleen Lane. “Protecting our natural resources is a priority and this is a small way to invest in the community,” Environmentalist Specialist Kara Taylor said. “Stream Team cleanup events are an opportunity to not...
First151719Last