Eastbound Lanes of Southwest Third Street to Remain Closed Through November

Eastbound Lanes of Southwest Third Street to Remain Closed Through November

The eastbound lanes of Southwest Third Street from Southwest Pryor Road to Southwest Murray Road are now expected to remain closed through November 2020, while one westbound lane of Southwest Third Street will remain open. Southwest Third Street will then reopen to two-way traffic as the contractor works on the remaining lanes. This work is necessary as part of the Third Street Improvements project.

Private utility relocation issues have had a significant impact on the contractor’s schedule. The new completion date for the project is late spring 2021. Depending on the weather and the project’s progress, the contractor may have to stop work over the winter months. Should a winter shutdown occur, the contractor is expected to do the following: restore two-way traffic on Southwest Third Street; positive drainage to ensure no standing water; no obstacles, such as street plates or raised manhole lids, for snowplows; north/south access across Southwest Third Street for Southwest Murray Road traffic; and access maintained for all property owners.

Construction is weather dependent, and schedules are subject to change. A project update will be provided as winter approaches.

For more information about the Third Street Improvements project, contact Public Works at 969-1800 or publicworks@cityofls.net.

Print

Latest News

Section of NE Short Street Set to Close Monday, April 22

Section of NE Short Street Set to Close Monday, April 22

Section of NE Short Street Set to Close Monday, April 22
A section of NE Short Street between NE Grand Avenue and NE Howard Avenue/NE Short Street is set to close on Monday, April 22, for approximately two weeks. The detour route includes NE Short Street, NE Ash Street, and NE Grand Avenue. The closure is necessary for stormwater improvements in the area. NE Ash Street had previously closed for this project and is now back open to traffic; however, an additional closure in the future will be necessary to finish curb and...
Section of SW McClendon Drive Set to Close April 8

Section of SW McClendon Drive Set to Close April 8

Section of SW McClendon Drive Set to Close April 8
A section of SW McClendon Drive between SW 1st Street and SW Peggy Circle is set to close on Monday, April 8, and will remain closed for approximately three months. The work is necessary for sanitary sewer work as part of the McClendon Ditch Sewer Improvements project. The detour route includes SW 1st Street, SW McClendon Drive, and SW 3rd Street. All work is weather permitting and schedules are subject to change.  
Change in Temporary Access for NW Quarry Park Road

Change in Temporary Access for NW Quarry Park Road

Change in Temporary Access for NW Quarry Park Road
Due to the closure of NW Quarry Park Road west of NW Pryor Road, a section of Noland Road between NW Quarry Park Road and Bannister Road has been reopened for temporary access as of Monday, April 1. The access on NW Clifford Road through Century Concrete is no longer available and should not be used.  
Section of NE Hideaway Drive Closing Today, April 1

Section of NE Hideaway Drive Closing Today, April 1

Section of NE Hideaway Drive Closing Today, April 1

A section of NE Hideaway Drive between NE Dalton’s Ridge Drive and NE Park Springs Terrace is closing today, Monday, April 1, and is expected to be closed for approximately one week. The closure is necessary for repairs to the roadway.

All work is weather permitting and schedules are subject to change.

SE Second Street Closure Extended

SE Second Street Closure Extended

SE Second Street Closure Extended
The closure of SE Second Street has been extended to SE Green Street. The section of SE 2nd Street from SE Green to SE Eastridge streets is now expected to remain closed through mid-May. Intermittent closures of SE Eastridge Street at SE Second Street are still expected while sanitary sewer work takes place. These closures are necessary for work associated with the Downtown Market Plaza project. City Hall Plaza will also be closed beginning April 1, and will...