Surface Seal Work Set to Begin on SE 2nd Street

Update: The contractor working on SE 2nd Street had an equipment failure earlier today, Tuesday, Nov. 1, and stopped work; however, work is tentatively expected to take place again from 9 a.m. – 4 p.m. tomorrow, Wed., Nov. 2. In order to complete surface sealing along SE 2nd Street at intersections, there will be short-term closures of Jefferson, Market, SE Main, Douglas and Green crossing SE 2nd Street. Eastbound and westbound traffic will be maintained along SE 2nd Street; however, traffic will not be able access the side streets from SE 2nd Street while intersection surface sealing is being completed.

Re-striping of SE 2nd Street is expected to take place under traffic next week, weather permitting.

The most recent schedule for surface seal indicates work could begin on SE 2nd Street between Route 291 and SW Jefferson Street on Thurs., Oct. 27, or Fri., Oct. 28, depending on weather. This work is expected to take 3-5 days which means it will likely continue into the following week.

Surface sealing will take place under traffic, and access will be maintained for business and property owners at all times; however, delays are expected.

https://cityofls.net/public-works/street-programs-maintenance/pavement-management-programs

 

Print

Latest News

Section of Southwest Market Street Closed

Section of Southwest Market Street Closed

Section of Southwest Market Street Closed

A section of Southwest Market Street between Southwest First and Second streets is closed. Length of closure is unknown at this time but currently permitted through Nov. 8. The closure is necessary for installation of utilities and to restore the street. This work is development related for the Ellis Glen project.

 

Section of Northeast Hagan Road Set to Close Wednesday, Sept. 25

Section of Northeast Hagan Road Set to Close Wednesday, Sept. 25

Section of Northeast Hagan Road Set to Close Wednesday, Sept. 25
A section of Northeast Hagan Road at Northeast Maguire Boulevard is set to close on Wednesday, September 25, for approximately three weeks. Northeast Maguire Boulevard is also closed to through traffic between Northeast Independence Avenue and Northeast Hagan Road. The closures are necessary for water main work associated with the Hangar 2 project at the Lee’s Summit Municipal Airport. The detour routes include Northeast Jones Industrial Drive and Northeast...
Section of Southeast Shenandoah Drive Set to Close Monday, Sept. 23

Section of Southeast Shenandoah Drive Set to Close Monday, Sept. 23

Section of Southeast Shenandoah Drive Set to Close Monday, Sept. 23

A section of Southeast Shenandoah Drive from Southeast Cumberland Drive to Southeast Ashton Drive is set to close on Monday, Sept. 23, for approximately one week. The detour route includes Southeast Cumberland Drive, Southeast Blue Parkway, and Southeast Battery Drive.

 

Section of Southeast Sixth Terrace Closed

Section of Southeast Sixth Terrace Closed

Section of Southeast Sixth Terrace Closed
A section of Southeast Sixth Terrace from Southeast Pendleton Drive to Southeast Ashton Drive is closed for approximately two weeks. Access will be allowed for residents. The detour route is Southeast Ashton Drive, Southeast Shenandoah Drive, and Southeast Cumberland Drive. The closure is necessary for sanitary sewer replacement. For more information, contact Public Works at publicworks@cityofls.net or 816-969-1800.  
Section of Southeast Green Street Set to Close Monday, Aug. 5

Section of Southeast Green Street Set to Close Monday, Aug. 5

Section of Southeast Green Street Set to Close Monday, Aug. 5
A section of Southeast Green Street between Southeast Second Street and the entrance into the City Hall parking lot and garage is set to close on Monday, Aug. 5, until approximately November. Access into the City Hall parking lot and garage from Southeast Green Street will be closed. Employees and visitors can enter the parking lot and garage from the alley just west of the garage off of Southeast Second Street. The closure is necessary for continued work on the...