Legacy Lake Dredging Project

Legacy Lake Dredging Project

 

Lee’s Summit Parks and Recreation is undertaking a major restoration effort at Legacy Lake to protect one of the community’s most important environmental and recreational assets. The Legacy Lake Dredging Project began in November 2025 and is scheduled for completion in May 2026.

Why Legacy Lake Matters

Legacy Lake is a vital resource within Legacy Park, serving both the community and the environment. The 28-acre lake provides essential habitat for a wide variety of wildlife, including fish, turtles, snakes, and migratory birds that rely on the lake as a stopping point during seasonal migrations. It also offers popular recreational opportunities, including fishing, paddleboarding, canoeing, and kayaking.

Beyond recreation, Legacy Lake plays a critical operational role. The lake supplies irrigation water for all sports fields and the amphitheater turf within Legacy Park and serves as a fire-suppression resource for park facilities. The park was intentionally designed so that stormwater runoff from the park and surrounding areas flows back into the lake, creating a self-sustaining system with a total watershed of 2.66 square miles.

Since 2014, the lake has provided approximately 44.6 million gallons of irrigation water annually at no cost, resulting in an estimated $370,000 in yearly savings. Over the lake’s 23-year lifespan, this has amounted to more than $8 million in total savings for the department.

The Need for Dredging

In 2019, an engineering survey revealed that approximately 50,000 cubic yards of sediment had accumulated on the lake bottom. This sediment buildup reduced the lake’s average depth by at least three feet and decreased its water capacity by approximately 30 percent.

The reduced water volume has significantly impacted irrigation operations, requiring Lee’s Summit Parks and Recreation to implement a “drought irrigation plan” for the past three years. While minimum water levels for fire suppression have been maintained, they remain at risk. In addition, the sediment buildup has negatively affected the lake’s ecological health. Shallower water allows invasive aquatic plants to establish, altering oxygen levels and contributing to algae growth along the shoreline.

The only long-term solution to restore the lake’s depth, capacity, and overall health is dredging.

Engineering and Project Planning

To address the issue, LSPR partnered with HDR, an engineering firm, to complete a Preliminary Engineering Report evaluating dredging options and costs. HDR recommended the use of a hydraulic dredge, which removes sediment while maintaining lake water levels and pumps the material to a settling pond.

HDR completed a bathymetric survey to determine the amount of sediment that must be removed to restore the lake to its original depth. Additional topographic and geotechnical surveys were conducted at the proposed settling pond site east of the amphitheater, including soil borings to a depth of 12–15 feet. No rock or subsurface conditions were identified that would hinder construction, and environmental reviews confirmed that the project would have no impact on bat habitats. The budget determined for this project is $1.8 million.

Dredging Process and Timeline

The Legacy Lake dredging project is being completed in several phases:

  • Development and construction of the sediment settling pond

  • Installation of silt transfer and water return pipes

  • Dredging of the lake

  • Removal of transfer piping

  • Sediment dehydration period

  • Rough grading of the disposal area

  • Final grading and seeding

Long-Term Benefits

Dredging Legacy Lake will restore its original depth and water capacity, improving irrigation reliability, protecting fire suppression reserves, and enhancing overall water quality. The project will also improve habitat conditions for aquatic life and reduce algae growth, helping ensure the lake remains a healthy, attractive, and functional centerpiece of Legacy Park.

Lee’s Summit Parks and Recreation is committed to the long-term stewardship of Legacy Lake. This investment will ensure the lake continues to serve the community, the environment, and park operations for decades to come.

Print

Latest News

Various Lane Closures Expected on Northeast Douglas Street Through End of March

Various Lane Closures Expected on Northeast Douglas Street Through End of March

Northeast Douglas Street between Northeast Chipman Road and Southeast Second Street will have various lane closures through the end of March for tree work. Work may start as early as this week, and is expected to take place a block at a time. Some detours may be needed depending on conditions. The work is in preparation for the Northeast Douglas Street Improvements project, which is expected to begin this summer 2026. For more information, contact the Public Works...
Public Meeting for Southeast Douglas Street Improvements Set for March 26

Public Meeting for Southeast Douglas Street Improvements Set for March 26

The City of Lee’s Summit will host an in-person public meeting for the design of the Southeast Douglas Street from Blue Parkway to Fourth Street Improvements project from 4:30 – 6:30 p.m. on Thursday, March 26, 2026, in the Strother Conference Room at Lee’s Summit City Hall, 220 SE Green St., Lee’s Summit, Mo. The meeting will be an open house-style format and there will not be a formal presentation; the public can come and go as schedules...
Section of Southeast Browning Street Set to Close Wednesday, March 11

Section of Southeast Browning Street Set to Close Wednesday, March 11

Section of Southeast Browning Street Set to Close Wednesday, March 11
A section of Southeast Browning Street between Southeast Eighth Street and Southeast Blue Parkway is set to close on Wednesday, March 11, until Monday, March 16. The work is necessary for concrete work as part of the Route 291 north and U.S. 50 Interchange project. The detour route includes Southeast Douglas Street, Southeast Seventh Street, Southeast Green Street, and Southeast Eighth Street.  
Northwest Olive and Northwest Orchard Streets Set to Close to Through Traffic Beginning Monday, March 2

Northwest Olive and Northwest Orchard Streets Set to Close to Through Traffic Beginning Monday, March 2

Northwest Olive and Northwest Orchard Streets Set to Close to Through Traffic Beginning Monday, March 2

Northwest Olive and Northwest Orchards streets are set to close to through traffic beginning, Monday, March 2, until October 2026. Northwest Central Street and Northeast Main Street also will be closed to through traffic. These initial closures are to minimize traffic while crews begin tree clearing and utility work. Local access will be maintained.

245Last