Section of Southwest Sampson Road Set to Close Wednesday, March 19

Section of Southwest Sampson Road Set to Close Wednesday, March 19

A section of Southwest Sampson Road between Southwest Scherer and Southwest Hook roads is set to close to thru traffic on Wednesday, March 19, and will remain closed until approximately mid-October 2025, for two phases of the Sampson Road Stormwater Improvements project.

Phase one includes culvert work just south of Southwest Scherer Road, and is expected to last until approximately the end of May 2025. The detour route includes Southwest Scherer Road, Southwest Ward Road, and Southwest Hook Road. All schedules are weather permitting and subject to change.

Phase two includes bridge replacement over Mouse Creek, and is expected to begin in mid-May and last until mid-October. Southwest Sampson Road between Southwest Scherer and Southwest Hook roads will remain closed to thru traffic during this work. A phase two closure map will be provided closer to the start date.

The Sampson Road Stormwater Improvements project will construct a bridge to accommodate pedestrians and cyclists, restore and stabilize the natural stream channel, open the floodway to reduce backwater flooding upstream, install stormwater best management practices (BMPs),  and construct a Mouse Creek Trail crossing for the Parks Department to support the Greenway Master Plan.

For more information, contact the Public Works Department at publicworks@cityofls.net or 816.969.1800.

Print

Latest News

City Preparing for Potential Freezing Rain Tomorrow, Wednesday, February 5

City Preparing for Potential Freezing Rain Tomorrow, Wednesday, February 5

A City crew is scheduled to report at midnight to treat streets with salt before potential freezing rain tomorrow morning, Wednesday, February 5. Streets may become slick due to pavement temperatures being below freezing. Drivers should use caution during the morning commute, especially on elevated surfaces such as bridges and overpasses. Pavement temperatures are expected to rise above freezing by mid-morning Wednesday.

 

Intersection of Southwest Third and Jefferson Streets Set to Close Monday, February 24

Intersection of Southwest Third and Jefferson Streets Set to Close Monday, February 24

Intersection of Southwest Third and Jefferson Streets Set to Close Monday, February 24

Update: This closure is postponed until Monday, February 24, due to the forecast for snow and subfreezing temperatures the week of February 17.

The intersection of Southwest Third and Jefferson streets is set to close on Monday, February 24, and will remain closed until approximately early April. The closure is necessary for water main work and intersection improvements. Detour routes include Southwest Blue Parkway, Southwest Second Street, Southwest Market Street, and Southwest Fourth Street. Local access only is available west and east of the closure on Southwest Third Street, and to the north and south of...
Green Street Project Update: Intersection of Southeast Third and Southeast Green Streets Now Open

Green Street Project Update: Intersection of Southeast Third and Southeast Green Streets Now Open

Green Street Project Update: Intersection of Southeast Third and Southeast Green Streets Now Open
The intersection of Southeast Third and Southeast Green streets is now open. The section of Southeast Third Street between Southeast Green Street and Southeast Grand Avenue, as well as the intersection of Southeast Third and Southeast Johnson streets, remains closed until March. The detour route remains Southeast Douglas Street, Southeast Second Street, and Southeast Grand Avenue. The closures are necessary for ongoing construction work related to the Green...
Section of Southwest Sampson Road Set to Close Monday, Feb. 3

Section of Southwest Sampson Road Set to Close Monday, Feb. 3

Section of Southwest Sampson Road Set to Close Monday, Feb. 3
Update 3/11/25: The closure is now expected on March 19.  Update 1/30/25: The closure of Southwest Sampson Road has been postponed until further notice due to emergency access issues. A section of Southwest Sampson Road between Southwest Scherer and Southwest Hook roads is set to close to thru traffic on Monday, Feb. 3, and will remain closed until approximately mid-August, for two phases of the Sampson Road Stormwater Improvements project. Phase one...
Section of Southwest Second Street Set to Close on Monday, Feb. 3

Section of Southwest Second Street Set to Close on Monday, Feb. 3

Section of Southwest Second Street Set to Close on Monday, Feb. 3

Update: This closure has been extended by one week and will open by 5 p.m. on Monday, February 17, 2025.

A section of Southwest Second Street between Southwest Noel and Market streets is set to close on Monday, Feb. 3, for one week. The closure is necessary for rehabilitation to failing sanitary sewer manholes located in the street. The detour route includes Southwest Noel Street, Southwest Third Street, and Southwest Market Street.

 