Green Street Project Update: SE Green Street Entrance into City Hall Now Open

The Southeast Green Street entrance into the Lee’s Summit City Hall parking lot and garage is now open.

Work on the Green Street project continues, and Southeast Third Street between Southeast Douglas Street and Southeast Grand Avenue remains closed to thru traffic.

Updates to estimated reopening dates are as follows:

  • Southeast Third Street from the alley by City Hall through the Southeast Green Street intersection is expected to open in early January 2025.
  • Southeast Third Street from Southeast Green Street through the Southeast Johnson Street intersection is expected to open in late February 2025.

All work is weather permitting and schedules are subject to change.

Print

Latest Press Releases

Summit Waves Aquatic Facility

Summit Waves Aquatic Facility

A teen party rental scheduled for the evening of August 6 at Summit Waves was canceled by Lee’s Summit Parks and Recreation after it became aware of social media posts advertising the event. This raised serious concerns about the safety of party guests and the possibility the event would grow beyond the capacity of staff. After multiple attempts to reach the renter in advance of the event to discuss safety concerns, a connection was not made until the...