REVISED MoDOT Update: Closures on MO 291 and U.S. 50 in Lee's Summit for bridge replacement operations Now - November 2026

The following information is shared from the Missouri Department of Transportation (MoDOT) and is related to the 291 North and US Route 50 Interchange project. https://www.modot.org/node/94913

Projects: Missouri Route 291 North and U.S. Route 50 Interchange Improvements in Jackson

JACKSON COUNTY – The Missouri Department of Transportation will conduct various closures and traffic modifications on Missouri Route 291 and U.S. MO 50 for bridge replacement operations. All work is weather permitting. See below for traffic modifications:

(Additional dates and modifications added)

Friday, Aug. 14 - Saturday Aug. 15 between 7:00am-3:00pm

  • Various lane closures on north and southbound MO 291 from SE Oldham to North of Bayberry.

Tuesday, Aug. 18 at 9:00am

  • Place traffic on the new Blue Parkway east and west of MO 291.

Tuesday, Aug. 18 at 12:00pm until Friday, Nov. 13 at 5:00pm

  • Close southbound MO 291 from Blue Parkway to the south side of U.S. 50. Motorists are encouraged to utilize Blue Parkway to Todd George.

Added: Wed., Aug. 19 7:00 p.m. until Thu., Aug. 20 6:00 a.m.

  • Close the right lane on WB U.S. 50 from west of Todd George to MO 291.

Added: Thu., Aug. 20 between 9:00 a.m. and 12:00 p.m.

  • Close the ramp from MO 291 to WB U.S. 50.

Added: Thu., Aug. 20 between 12:00 p.m. and 4:00 p.m.

  • Close the ramp from MO 291 to EB U.S. 50.

Added: Thu., Aug. 20 at 8:00 p.m. until Fri., Aug. 21 at 6:00 a.m.

  • Close the right lane on EB U.S. 50 from MO 291 south (Jefferson St) to MO 291 and close the EB off ramp to MO 291.

Fri., Sep. 11 at 10:00 a.m. until Fri., Nov. 13 at 5:00 p.m.

  • Close NB MO 291 from the south side of U.S. 50 to the north side of U.S. 50.

Fri., Sep. 11 at 3:00 p.m.

  • Open WB U.S. 50 to MO 291 (Right Turn Movement Only).

Fri., Sep. 11 between 8:00 p.m. and 10:00 p.m.

  • Close the right lane on WB U.S. 50 from west of Todd George to west of MO 291.
  • Close the left lane on EB U.S. 50 west of MO 291 to east of MO 291.

Fri., Sept. 11 at 10:00 p.m. until Mon., Sept. 14 at 6:00 a.m.

Bridge demo traffic modifications:

  • Close the left lane on WB U.S. 50 west of Todd George to the WB U.S. 50 off ramp. Traffic will be diverted to go up and over the ramp back to U.S. 50.
  • Close the left lane on EB U.S. 50 west of MO 291 to the MO 291 off ramp. Traffic will be diverted to go up and over the ramp back to U.S. 50.

This is part of a larger project at MO 291N and U.S. 50, which includes bridge replacement, road realignment, and ADA improvements from SE 7th Terrace to SE Oldham Parkway in Lee’s Summit with a completion date of January 2027. To learn more about the project visit: Missouri Route 291 North and U.S. Route 50 Interchange Improvements in Jackson | Missouri Department of Transportation

Motorists are reminded to slow down and pay attention while driving in work zones. Not all work zones look alike. Work zones can also be short-term, temporary lane closures to make quick repairs or remove debris form the roadway.

For more information about MoDOT news, projects or events, please visit our website at www.modot.org.kansascity. For instant updates, follow MoDOT_KC on X, or share posts and comments on our Facebook at www.facebook.com/MoDOT.KansasCity/. MoDOT Kansas City maintains more than 7,000 miles of state roadway in nine counties. Sign up online for workzone updates or call 888-ASK-MODOT.

Print

Latest News

City Crews Plowing Streets Today, Thurs., Dec. 22

City Crews Plowing Streets Today, Thurs., Dec. 22

The City’s crews are plowing streets today, Thurs., Dec. 22, and will continue plowing tonight and overnight into tomorrow, Fri., Dec. 23. Crews are completing primary streets and then will move into secondary streets, and expect to continue plowing secondary and residential streets overnight into Friday. No additional precipitation is predicted at this time and crews expect it may take 32.5 hours to plow all streets in the City after accumulating snow ended;...
City Crews Preparing for Winter Storm

City Crews Preparing for Winter Storm

The City’s crews began pre-treating residential streets today, Wed., Dec. 21, in preparation for the upcoming winter storm which is expected to start with a wintry mix of drizzle and light snow after 10 p.m. tonight. Crews reported at 7 p.m. tonight to finish pre-treating residential and secondary streets, and will continue pre-treating primary streets tonight and overnight into Thurs., Dec. 22, until temperatures plummet at which time salting operations will...
City Crews Treated Streets Today, Mon., Dec. 19; Preparing for Chance of Freezing Drizzle Tues., Dec. 20

City Crews Treated Streets Today, Mon., Dec. 19; Preparing for Chance of Freezing Drizzle Tues., Dec. 20

The City’s crews continued to treat streets with salt today, Mon., Dec. 19, and are expected to end operations at 3:30 p.m. due to the forecast for rain and non-accumulating snow this afternoon. Crews are expected to report again at 7 p.m. tonight to continue to monitor conditions and treat streets as needed late Monday, and overnight into Tues., Dec. 20. The City’s crews are also preparing for a chance of freezing drizzle during the early morning...
City Crews Preparing for Snow on Mon., Dec. 19

City Crews Preparing for Snow on Mon., Dec. 19

The City's crews are preparing for snow to begin around 6 a.m. on Mon., Dec. 19. Crews are expected to report at 9 p.m. tonight, Sun., Dec. 18, to begin pre-treatment with salt, and treatment will continue throughout the event as needed. Temperatures are expected to be below freezing when the snow starts, and the Monday morning commute may be slick. Residents are encouraged to use caution while driving especially on elevated surfaces such as...
City Crews Preparing for Snow Mon., Nov. 14, and Overnight Into Tues., Nov. 15

City Crews Preparing for Snow Mon., Nov. 14, and Overnight Into Tues., Nov. 15

The City’s crews are preparing equipment and pre-treating hot spot areas such as major intersections and bridges with rock salt today, Mon. Nov. 14, in anticipation of snow later tonight and overnight into Tues., Nov. 15. Crews are currently on standby and will be called in as necessary overnight based on the forecast and conditions. Precipitation is expected to start as light rain changing over to snow. Pavement temperatures will hover around freezing, and...
First485052Last