REVISED MoDOT Update: Closures on MO 291 and U.S. 50 in Lee's Summit for bridge replacement operations Now - November 2026

The following information is shared from the Missouri Department of Transportation (MoDOT) and is related to the 291 North and US Route 50 Interchange project. https://www.modot.org/node/94913

Project: Missouri Route 291 North and U.S. Route 50 Interchange Improvements in Jackson

JACKSON COUNTY – The Missouri Department of Transportation will conduct various closures and traffic modifications on Missouri Route 291 and U.S. MO 50 for bridge replacement operations. All work is weather permitting. See below for traffic modifications (all times listed are approximate):

Additional dates and modifications added

Friday, Aug. 14 - Saturday Aug. 15 between 7:00am-3:00pm

  • Various lane closures on north and southbound MO 291 from SE Oldham to North of Bayberry.

Tuesday, Aug. 18 at 9:00am

  • Place traffic on the new Blue Parkway east and west of MO 291.

Tuesday, Aug. 18 at 12:00pm until Friday, Nov. 13 at 5:00pm

  • Close southbound MO 291 from Blue Parkway to the south side of U.S. 50. Motorists are encouraged to utilize Blue Parkway to Todd George.

Added: Wed., Aug. 19 7:00 p.m. until Thu., Aug. 20 6:00 a.m.

  • Close the right lane on WB U.S. 50 from west of Todd George to MO 291.

Added: Thu., Aug. 20 between 9:00 a.m. and 12:00 p.m.

  • Close the ramp from MO 291 to WB U.S. 50.

Added: Thu., Aug. 20 between 12:00 p.m. and 4:00 p.m.

  • Close the ramp from MO 291 to EB U.S. 50.

Added: Thu., Aug. 20 at 8:00 p.m. until Fri., Aug. 21 at 6:00 a.m.

  • Close the right lane on EB U.S. 50 from MO 291 south (Jefferson St) to MO 291 and close the EB off ramp to MO 291.

Added 8/25/26: (TODAY) Tuesday, August 25 at 9:00 a.m. - 3:00 p.m.

  • Close the right lane on NB 291 from SE Oldham to South of Blue Parkway.
  • Close the right lane on SB 291 from Bayberry to 50 Highway.

Added 8/25/26: The Missouri Department of Transportation will CLOSE the ramp from MO 291 to westbound U.S. 50 in Lee’s Summit for bridge project operations beginning tomorrow, Aug. 26 between 9 a.m. and 3 p.m. All work is weather permitting.

Fri., Sep. 11 at 10:00 a.m. until Fri., Nov. 13 at 5:00 p.m.

  • Close NB MO 291 from the south side of U.S. 50 to the north side of U.S. 50.

Fri., Sep. 11 at 3:00 p.m.

  • Open WB U.S. 50 to MO 291 (Right Turn Movement Only).

Fri., Sep. 11 between 8:00 p.m. and 10:00 p.m.

  • Close the right lane on WB U.S. 50 from west of Todd George to west of MO 291.
  • Close the left lane on EB U.S. 50 west of MO 291 to east of MO 291.

 

Tues. Sept. 8, at 4:00 a.m. until Fri. Nov. 13 at 5:00 p.m.

  • Close NB 291 from Oldham to Blue Parkway
  • Close SB 291 from Blue Parkway to Oldham

Tues. Sept. 8 at 4:00 a.m. until Mon. Sept. 14 at 5:00 p.m.

  • Close the Right Lane EB U.S. 50 from Jefferson to NB MO 291
  • Close ramp from EB U.S. 50 to NB MO 291
  • Close the acceleration lane on the ramp from MO 291 to EB U.S. 50 (barrier wall removal)
  • Close the acceleration lane on the ramp from MO 291 to WB U.S. 50 (barrier wall removal)

Mon. Sept. 14  from 9:00 a.m.- 3:00 p.m.

  • Various intermittent lane closures EB/WB U.S. 50 for striping operations

Fri., Sept. 11 at 10:00 p.m. until Mon., Sept. 14 at 6:00 a.m. REVISED: Mon. Sept. 14 at 10:00 p.m. until Mon. Sept. 21 at 6:00 a.m.

Bridge demo traffic modifications:

  • Close the left lane on WB U.S. 50 west of Todd George to the WB U.S. 50 off ramp. Traffic will be diverted to go up and over the ramp back to U.S. 50.
  • Close the left lane on EB U.S. 50 west of MO 291 to the MO 291 off ramp. Traffic will be diverted to go up and over the ramp back to U.S. 50.

Mon. Sept. 21 at 3:00 p.m. until Fri. Nov. 13 at 5:00 p.m.

  • Various lane closures on EB/WB U.S. 50 at MO 291. The off ramps to MO 291 will be limited to right turns only.

This is part of a larger project at MO 291N and U.S. 50, which includes bridge replacement, road realignment, and ADA improvements from SE 7th Terrace to SE Oldham Parkway in Lee’s Summit with a completion date of January 2027. To learn more about the project visit: Missouri Route 291 North and U.S. Route 50 Interchange Improvements in Jackson | Missouri Department of Transportation

Motorists are reminded to slow down and pay attention while driving in work zones. Not all work zones look alike. Work zones can also be short-term, temporary lane closures to make quick repairs or remove debris form the roadway.

For more information about MoDOT news, projects or events, please visit our website at www.modot.org.kansascity. For instant updates, follow MoDOT_KC on X, or share posts and comments on our Facebook at www.facebook.com/MoDOT.KansasCity/. MoDOT Kansas City maintains more than 7,000 miles of state roadway in nine counties. Sign up online for workzone updates or call 888-ASK-MODOT.

Print

Latest News

Utility Work Along Southeast Second Street

Utility Work Along Southeast Second Street

Utility Work Along Southeast Second Street
A utility contractor is completing work along the south side of Southeast Second Street between Southeast Main Street and the alley behind the City Hall parking garage which will require the closure of sidewalk and two alleys, and the closure of Southeast Douglas Street at Southeast Second Street. Work will take place daily from 9 a.m. to 4 p.m. and is permitted from now until November 26. As a condition of permit approval, operations along Southeast Second Street...
Section of Southeast Fourth Street Set to Close Monday, Oct. 27 (postponed from Oct. 23)

Section of Southeast Fourth Street Set to Close Monday, Oct. 27 (postponed from Oct. 23)

Section of Southeast Fourth Street Set to Close Monday, Oct. 27 (postponed from Oct. 23)

Update: Southeast Fourth Street is open to traffic as of 11/14/25.

A section of Southeast Fourth Street between Southeast Timbercreek Lane and Southeast Todd George Parkway is set to close on Monday, Oct. 27, until Monday, Nov. 17 (postponed and extended due to weather and utility conflicts from Monday, Oct. 23, through Monday, Nov. 3). The detour route includes Southeast Timbercreek Lane, Southeast Winburn Trail, and Southeast Todd George Parkway.

Section of Southeast Browning Street Set to Close Thursday, Oct. 23 (postponed from Oct. 22)

Section of Southeast Browning Street Set to Close Thursday, Oct. 23 (postponed from Oct. 22)

Section of Southeast Browning Street Set to Close Thursday, Oct. 23 (postponed from Oct. 22)
A section of Southeast Browning Street between Southeast Eighth Street and Southeast Blue Parkway was set to close on Thursday, Oct. 23 (postponed from Oct. 22), through Friday, Nov. 21 (extended from Nov. 7). The work is necessary for water line work as part of the Route 291 north and U.S. 50 Interchange project. Also on Thursday, Oct. 23 (postponed from Oct. 22), Southeast Douglas Street north of Southeast Blue Parkway will reopen but Southeast Ninth Street will...
Northwest Colbern Road Now Open

Northwest Colbern Road Now Open

Northwest Colbern Road Now Open

Update 11/26/25: Northwest Main Street is now open.

Northwest Colbern Road between Northwest Blue Parkway and Northeast Douglas Street is now open to traffic.

Please note there will be some ongoing work along the corridor, and Northwest Main Street at Northwest Colbern Road will remain closed for approximately one month.

Intersection of Southwest Scherer and Southwest Pryor Roads Set to Close Wednesday, Oct. 22

Intersection of Southwest Scherer and Southwest Pryor Roads Set to Close Wednesday, Oct. 22

Intersection of Southwest Scherer and Southwest Pryor Roads Set to Close Wednesday, Oct. 22
Update 12/12/25: Southwest Scherer Road is now open. Update 12/5/25: The closure of Southwest Scherer Road at its intersection with Southwest Pryor Road has been extended by one week. It was originally scheduled to reopen today 12/5/25. The intersection of Southwest Scherer and Southwest Pryor Roads is set to close on Wednesday, October 22, for approximately forty-five days. The closure is necessary for intersection reconstruction.