Colbern Road Safety Improvement Work Begins September 5

Colbern Road Safety Improvement Work Begins September 5

The City of Lee’s Summit announced that work on the Colbern Road Improvements Project begins Sept. 5. The project will improve the safety and flow of traffic on Northwest Colbern Road between Northeast Douglas Street and Missouri Route 350 and will require that section of road to be closed to through traffic until spring 2025.  

The first phase of construction will require a complete closure of Northwest Colbern Road from approximately Missouri Route 350 through the roundabout at Northwest Blue Parkway. This phase includes the reconstruction of the roundabout and realignment of Northwest Blue Parkway from the roundabout to the frontage road along Unity Village. This closure will continue through spring 2024, weather permitting. Detours will be put in place and signage will mark the detour route. Once this phase is complete, Northwest Colbern Road from Missouri Route 350 through the roundabout will reopen. Northwest Colbern Road from Missouri Route 350 to Northeast Douglas Street will remain closed to through traffic until spring 2025.

“With a cost of $30 million, the Colbern Road Improvements Project is the largest capital improvement project in the history of Lee’s Summit. It is a huge transportation improvement for vehicular, freight, bicycle, and pedestrian capacity and safety and supports our City’s long-term community growth,” said Lee’s Summit Mayor Bill Baird. “In addition to funding from the 2017 Capital Improvement Sales Tax and water and sewer funds, we were fortunate to receive grant funding for this project from the federal Surface Transportation Program and the Governor’s Transportation Cost-Share Program. This project was one of 20 transportation projects across the state selected to receive funding from the Governor’s Transportation Cost-Share Program based in part on its economic impact and public benefit.”

The Colbern Road Improvements Project will widen Northwest Colbern Road to four lanes with turn lanes, sidewalks, shared-use paths, curbs and gutters, street lighting and bridge replacement over the Union Pacific Railroad, including bicycle and pedestrian accommodations. These improvements will not only improve the safety of the road but will accommodate future traffic projections. 

For more information about the project, contact Public Works at 969.1800 or publicworks@cityofls.net.

Print

Latest News

Section of Southeast Johnson Street Set to Close Monday, July 8

Section of Southeast Johnson Street Set to Close Monday, July 8

Section of Southeast Johnson Street Set to Close Monday, July 8
A section of Southeast Johnson Street between Southeast Second and Southeast Third streets is set to close on Monday, July 8, for approximately two months. The closure is necessary for continued infrastructure work associated with the Downtown Market Plaza project. The detour route includes Southeast Grand Avenue, Southeast Third Street, Southeast Douglas Street, and Southeast Second Street. All work is weather permitting and schedules are subject to...
Section of Arboridge Drive Closed for Construction

Section of Arboridge Drive Closed for Construction

Section of Arboridge Drive Closed for Construction

On June 24, a section of Arboridge Drive will close between Missouri 150 Highway and Southwest Arborwalk Boulevard for the construction of a southbound turn lane. This is a full closure lasting until July 15. Detour routes have been provided. All schedules are weather permitting and subject to change.

Northwest Colbern Road Improvements Project Traffic Changes Set for Friday, June 14

Northwest Colbern Road Improvements Project Traffic Changes Set for Friday, June 14

Northwest Colbern Road Improvements Project Traffic Changes Set for Friday, June 14
Update 6/13/24: These traffic changes are delayed until next Wednesday, June 19. Phase one of the Northwest Colbern Road Improvements project is nearing completion, and phase two traffic changes are set to begin on Friday, June 14. The section of Northwest Colbern Road from approximately Missouri Route 350 to east of the roundabout at NW Blue Parkway is set to reopen, and a section of Northwest Colbern Road between the roundabout and Northeast Douglas Street is...
Section of Northeast Rice Road Closed for Stormwater Repairs

Section of Northeast Rice Road Closed for Stormwater Repairs

Section of Northeast Rice Road Closed for Stormwater Repairs

A section of Northeast Rice Road at Northeast Mulberry Street is closed for stormwater repairs. The road will be closed until all work has been completed.

A sinkhole had developed due to a rusted corrugated metal storm line. Crews will be replacing the storm line from storm box to storm box. 

For more information, contact the Public Works Department at publicworks@cityofls.net or 816-969-1800.

Section of Northeast Hagan Road Set to Close June 10

Section of Northeast Hagan Road Set to Close June 10

Section of Northeast Hagan Road Set to Close June 10
Update: As of 7/1/24, this section of Northeast Hagan Road is now open. A section of Northeast Hagan Road at Northeast Maguire Boulevard is set to close on Monday, June 10, for approximately three weeks. Northeast Maguire Boulevard is also closed to through traffic between Northeast Independence Avenue and Northeast Hagan Road. The closures are necessary for water main work associated with the Hangar 2 project at the Lee’s Summit Municipal Airport. The...