Chipman Road Project Update

Chipman Road Project Update

The Chipman Road Improvements project is moving into the next construction phase beginning the week of Feb.10, weather permitting. Pavement removal is expected to start on the section of Northwest Chipman Road from just west of the pedestrian bridge to Northwest Bent Tree Drive in preparation for paving in March. This section will remain closed until construction is complete later this spring. The section of Northwest Chipman Road between View High Drive and just west of the pedestrian bridge is open to local traffic only. The detour route remains Northwest Pryor Road, Southwest Third Street and View High Drive.

The Chipman Road Improvements project began in mid-July 2023. Improvements completed to date include the connection of Northwest Ashurst Drive to View High Drive, realignments of both Northwest Cedar Creek Lane and Northwest Edgewood Drive, and the new pedestrian bridge at the Rock Island Trail. Remaining work includes completion of a traffic signal at the intersection of View High Drive and Northwest Chipman Road, paving and completion of infrastructure improvements such as sidewalks, shared use path, streetlighting, enclosed stormwater drainage system and relocation and/or upsizing of water and sewer lines.

Northwest Chipman Road between View High Drive and Northwest Bent Tree Drive will remain closed to through traffic for the project's duration. The project is expected to be completed in late spring 2025.

For more information, contact Public Works at publicworks@cityofls.net or 816.969.1800.

Print

Latest News

City Crews Plowing and Treating Streets Today, Wed., Feb. 2

City Crews Plowing and Treating Streets Today, Wed., Feb. 2

The City’s crews are plowing and treating streets today, Wed., Feb. 2. Crews are finishing up primary streets, and then will move into secondary streets followed by residentials. There will be a break in the snow before a second round arrives this evening, and crews may have to move back into primary streets. Crews are scheduled to continue working around the clock. Snow totals are expected to be lower than originally predicted. The City will continue to...
City Crews Preparing for Snow Wed., Jan. 5, and Overnight Into Thurs., Jan. 6

City Crews Preparing for Snow Wed., Jan. 5, and Overnight Into Thurs., Jan. 6

The City’s Crews are preparing for another round of snow set to begin late Wed., Jan. 5, and continuing overnight into Thurs., Jan. 6. Crews began pretreating residential streets this morning and will work until 3:30 p.m. Another crew is then scheduled to begin working at 7 p.m. to pretreat primary and secondary streets, and will continue treating them during snowfall. Temperatures will be extremely cold and streets are expected to be slick as soon as...
First42434446