Chipman Road Project Update

Chipman Road Project Update

The Chipman Road Improvements project is moving into the next construction phase beginning the week of Feb.10, weather permitting. Pavement removal is expected to start on the section of Northwest Chipman Road from just west of the pedestrian bridge to Northwest Bent Tree Drive in preparation for paving in March. This section will remain closed until construction is complete later this spring. The section of Northwest Chipman Road between View High Drive and just west of the pedestrian bridge is open to local traffic only. The detour route remains Northwest Pryor Road, Southwest Third Street and View High Drive.

The Chipman Road Improvements project began in mid-July 2023. Improvements completed to date include the connection of Northwest Ashurst Drive to View High Drive, realignments of both Northwest Cedar Creek Lane and Northwest Edgewood Drive, and the new pedestrian bridge at the Rock Island Trail. Remaining work includes completion of a traffic signal at the intersection of View High Drive and Northwest Chipman Road, paving and completion of infrastructure improvements such as sidewalks, shared use path, streetlighting, enclosed stormwater drainage system and relocation and/or upsizing of water and sewer lines.

Northwest Chipman Road between View High Drive and Northwest Bent Tree Drive will remain closed to through traffic for the project's duration. The project is expected to be completed in late spring 2025.

For more information, contact Public Works at publicworks@cityofls.net or 816.969.1800.

Print

Latest News

City Crews Prepared for Winter Storm Jan. 8-9

City Crews Prepared for Winter Storm Jan. 8-9

The City’s crews are pre-treating streets due to a winter storm that began today, Monday, Jan. 8, and is expected to continue overnight into tomorrow, Tuesday, Jan. 9. A mix of rain and snow is expected throughout the day today, and pavement temperatures should remain above freezing until 10 p.m. tonight; however, heavy snow may overwhelm pavements at times and cause slushy conditions. Pavement temperatures will fall below freezing later tonight, and drivers...
City Crews Prepared for Snow This Weekend

City Crews Prepared for Snow This Weekend

The City’s crews prepared trucks and equipment due to light snow forecast for tonight, Friday, Jan. 5, and tomorrow, Saturday, Jan. 6. Pavement temperatures are expected to remain at or above freezing which should melt any snow on pavements; however, snow may become heavy at times and could overwhelm pavements. The City will continue to monitor the weather and will call out crews as needed for response. The City’s crews are also preparing for snow...
Section of NW Quarry Park Road Closed

Section of NW Quarry Park Road Closed

Section of NW Quarry Park Road Closed

A section of NW Quarry Park Road west of NW Pryor Road is closed to through traffic for an emergency road repair. The duration of the closure is unknown at this time. Access for emergency vehicles and residents will be provided on NW Valley Garden Drive/Clifford Road and Bannister Road.

City Crews Preparing for Snow Dec. 26-27

City Crews Preparing for Snow Dec. 26-27

The City has a small crew scheduled to report at 2 a.m. Wed., Dec. 27, to monitor conditions and treat streets with salt as needed due to the potential for snow. Temperatures overnight will hover around freezing which may cause slick conditions. Drivers should use caution during the Wednesday morning commute, especially on elevated surfaces such as bridges and overpasses. Snow is also expected today, Tues., Dec. 26, and may be heavy at times; however, pavement...
Joint Public Meeting for Douglas Street Improvements and Olive & Orchard Street and Stormwater Improvements Set for Jan. 18

Joint Public Meeting for Douglas Street Improvements and Olive & Orchard Street and Stormwater Improvements Set for Jan. 18

The City of Lee’s Summit will host an in-person public meeting to discuss the design of both the Douglas Street Improvements project and the Olive & Orchard Street and Stormwater Improvements from 4-6 p.m. on Thursday, Jan. 18, 2024, in the Council Chambers at Lee’s Summit City Hall, 220 SE Green St., Lee’s Summit, Mo. The meeting will be an open house-style format and there will not be a formal presentation; the public can come and go as...