Chipman Road Project Update

Chipman Road Project Update

The Chipman Road Improvements project is moving into the next construction phase beginning the week of Feb.10, weather permitting. Pavement removal is expected to start on the section of Northwest Chipman Road from just west of the pedestrian bridge to Northwest Bent Tree Drive in preparation for paving in March. This section will remain closed until construction is complete later this spring. The section of Northwest Chipman Road between View High Drive and just west of the pedestrian bridge is open to local traffic only. The detour route remains Northwest Pryor Road, Southwest Third Street and View High Drive.

The Chipman Road Improvements project began in mid-July 2023. Improvements completed to date include the connection of Northwest Ashurst Drive to View High Drive, realignments of both Northwest Cedar Creek Lane and Northwest Edgewood Drive, and the new pedestrian bridge at the Rock Island Trail. Remaining work includes completion of a traffic signal at the intersection of View High Drive and Northwest Chipman Road, paving and completion of infrastructure improvements such as sidewalks, shared use path, streetlighting, enclosed stormwater drainage system and relocation and/or upsizing of water and sewer lines.

Northwest Chipman Road between View High Drive and Northwest Bent Tree Drive will remain closed to through traffic for the project's duration. The project is expected to be completed in late spring 2025.

For more information, contact Public Works at publicworks@cityofls.net or 816.969.1800.

Print

Latest News

Section of NE Short Street Set to Close Monday, April 22

Section of NE Short Street Set to Close Monday, April 22

Section of NE Short Street Set to Close Monday, April 22
A section of NE Short Street between NE Grand Avenue and NE Howard Avenue/NE Short Street is set to close on Monday, April 22, for approximately two weeks. The detour route includes NE Short Street, NE Ash Street, and NE Grand Avenue. The closure is necessary for stormwater improvements in the area. NE Ash Street had previously closed for this project and is now back open to traffic; however, an additional closure in the future will be necessary to finish curb and...
Section of SW McClendon Drive Set to Close April 8

Section of SW McClendon Drive Set to Close April 8

Section of SW McClendon Drive Set to Close April 8
A section of SW McClendon Drive between SW 1st Street and SW Peggy Circle is set to close on Monday, April 8, and will remain closed for approximately three months. The work is necessary for sanitary sewer work as part of the McClendon Ditch Sewer Improvements project. The detour route includes SW 1st Street, SW McClendon Drive, and SW 3rd Street. All work is weather permitting and schedules are subject to change.  
Change in Temporary Access for NW Quarry Park Road

Change in Temporary Access for NW Quarry Park Road

Change in Temporary Access for NW Quarry Park Road
Due to the closure of NW Quarry Park Road west of NW Pryor Road, a section of Noland Road between NW Quarry Park Road and Bannister Road has been reopened for temporary access as of Monday, April 1. The access on NW Clifford Road through Century Concrete is no longer available and should not be used.  
Section of NE Hideaway Drive Closing Today, April 1

Section of NE Hideaway Drive Closing Today, April 1

Section of NE Hideaway Drive Closing Today, April 1

A section of NE Hideaway Drive between NE Dalton’s Ridge Drive and NE Park Springs Terrace is closing today, Monday, April 1, and is expected to be closed for approximately one week. The closure is necessary for repairs to the roadway.

All work is weather permitting and schedules are subject to change.

SE Second Street Closure Extended

SE Second Street Closure Extended

SE Second Street Closure Extended
The closure of SE Second Street has been extended to SE Green Street. The section of SE 2nd Street from SE Green to SE Eastridge streets is now expected to remain closed through mid-May. Intermittent closures of SE Eastridge Street at SE Second Street are still expected while sanitary sewer work takes place. These closures are necessary for work associated with the Downtown Market Plaza project. City Hall Plaza will also be closed beginning April 1, and will...