Section of Pryor Road Set to Open Friday, June 19

Section of Pryor Road Set to Open Friday, June 19

The section of Pryor Road between Longview and Scherer roads is expected to open to traffic by the end of the day tomorrow, Friday, June 19. One lane of traffic will be open in each direction, and it will remain an active construction zone with workers present so drivers should use caution. The posted detour will remain Longview, Ward, and Hook roads. The intersection of Pryor and Scherer roads will be a three-way stop.

The opening of Pryor Road south of Scherer Road to Eagle Creek Drive is delayed until July, due to utility conflicts.

Improvements to the Pryor and Longview intersection are complete, and work along Scherer Road is complete. Improvements to the Pryor and Hook intersection are expected to begin later this summer. The overall project is anticipated to be completed in summer 2027.

All work is weather permitting and schedules are subject to change. For updates and more information, visit the City’s project page at https://cityofls.net/pryor-road.

Print

Latest News

Ward Road Project Update - Section of NW Lincolnwood Drive Set to Close Monday, July 20

Ward Road Project Update - Section of NW Lincolnwood Drive Set to Close Monday, July 20

Ward Road Project Update - Section of NW Lincolnwood Drive Set to Close Monday, July 20

On Monday, July 20, NW Lincolnwood Drive is set to close at the intersection of Ward Road in order to pour the new intersection approach. Local traffic will be able to access NW Lincolnwood Drive from NW Woodbine Avenue in both directions.  Ward Road will also be open in both directions from NW Lincolnwood Drive to NW O’Brien Road.  The closure is expected to last approximately one week.

Night Work Scheduled July 19-24 for Pavement Management Programs

Night Work Scheduled July 19-24 for Pavement Management Programs

The City’s mill and overlay and surface seal programs both have night work scheduled July 19-24, to minimize disruptions to traffic on major roads. Night work will generally take place beginning at 8 p.m. at night and will continue overnight until 7 a.m. the next morning, from Sunday night, July 19, through Friday morning, July 24. All work is weather permitting and schedules are subject to change.

 

Section of SW Noel Street Set to Close Daily Beginning Monday, July 20

Section of SW Noel Street Set to Close Daily Beginning Monday, July 20

Section of SW Noel Street Set to Close Daily Beginning Monday, July 20

A section of SW Noel Street at SW 2nd Street is set to close daily from 9 a.m. to 4 p.m. beginning on Monday, July 20, and lasting for approximately two weeks. The detour route includes SW 2nd Street, SW Lakeview Boulevard, and NW Little Avenue.

 

Ward Road Project Update - Blue Parkway Roundabout Set to Open

Ward Road Project Update - Blue Parkway Roundabout Set to Open

Ward Road Project Update - Blue Parkway Roundabout Set to Open

The new roundabout on Blue Parkway at Ward Road is set to open to eastbound and westbound traffic by the end of the day today, Friday, July 10.

Ward Road will remain closed to through traffic between Blue Parkway and O’Brien Road.