Section of Pryor Road Set to Open Friday, June 19

Section of Pryor Road Set to Open Friday, June 19

The section of Pryor Road between Longview and Scherer roads is expected to open to traffic by the end of the day tomorrow, Friday, June 19. One lane of traffic will be open in each direction, and it will remain an active construction zone with workers present so drivers should use caution. The posted detour will remain Longview, Ward, and Hook roads. The intersection of Pryor and Scherer roads will be a three-way stop.

The opening of Pryor Road south of Scherer Road to Eagle Creek Drive is delayed until July, due to utility conflicts.

Improvements to the Pryor and Longview intersection are complete, and work along Scherer Road is complete. Improvements to the Pryor and Hook intersection are expected to begin later this summer. The overall project is anticipated to be completed in summer 2027.

All work is weather permitting and schedules are subject to change. For updates and more information, visit the City’s project page at https://cityofls.net/pryor-road.

Print

Latest News

Olive & Orchard Project Update: Road Closures for Stormwater Work Set for Week of Nov. 16

Olive & Orchard Project Update: Road Closures for Stormwater Work Set for Week of Nov. 16

Olive & Orchard Project Update: Road Closures for Stormwater Work Set for Week of Nov. 16
There are two upcoming road closures for stormwater work which are set to take place the week of November 16. NW Olive Street just north of NW Orchard Street is set to close Monday, November 16, through Tuesday, November 17. The detour route is intended to guide drivers from the south end of Olive over to Chipman and Douglas. NE Main Street just north of NW Orchard Street is set to close Wednesday, November 18, through Thursday, November 19.
Pryor Road Project Update - Hook Road Now Open

Pryor Road Project Update - Hook Road Now Open

Pryor Road Project Update - Hook Road Now Open

Hook Road at the Pryor Road intersection is now open in both directions between Horridge and Ward Roads.

Pryor Road to the south of Hook Road is now expected to open the week of November 16.

 

Snow Event Dry Run - City Crews Preparing for Winter Weather Season Today, Wednesday, November 4

Snow Event Dry Run - City Crews Preparing for Winter Weather Season Today, Wednesday, November 4

The City of Lee’s Summit is holding a snow event dry run from 7 a.m. to 3:30 p.m. today, Wednesday, November 4, to prepare for the upcoming 2026-2027 winter weather season. This exercise is an important part of the City’s annual preparation and helps ensure crews are ready to respond when winter weather arrives. City crews will be testing equipment and software, and driving snow routes with plows and salt spreaders installed on trucks. The purpose is...
Pryor Road Project Update - Intersection of River Run Drive and Pryor Road Set to Close Week of October 26

Pryor Road Project Update - Intersection of River Run Drive and Pryor Road Set to Close Week of October 26

Pryor Road Project Update - Intersection of River Run Drive and Pryor Road Set to Close Week of October 26

Update: This closure is likely to occur in the afternoon on Tuesday, Oct. 27.
The intersection of SW River Run Drive and SW Pryor Road is expected to close during the week of Oct. 26, until approximately the end of November. During this closure, school traffic will temporarily use the new SW 26th Terrace connection east of SW Pryor Road to access SW River Run Drive and the school.