Chipman Road Project Update

Chipman Road Project Update

The Chipman Road Improvements project is moving into the next construction phase beginning the week of Feb.10, weather permitting. Pavement removal is expected to start on the section of Northwest Chipman Road from just west of the pedestrian bridge to Northwest Bent Tree Drive in preparation for paving in March. This section will remain closed until construction is complete later this spring. The section of Northwest Chipman Road between View High Drive and just west of the pedestrian bridge is open to local traffic only. The detour route remains Northwest Pryor Road, Southwest Third Street and View High Drive.

The Chipman Road Improvements project began in mid-July 2023. Improvements completed to date include the connection of Northwest Ashurst Drive to View High Drive, realignments of both Northwest Cedar Creek Lane and Northwest Edgewood Drive, and the new pedestrian bridge at the Rock Island Trail. Remaining work includes completion of a traffic signal at the intersection of View High Drive and Northwest Chipman Road, paving and completion of infrastructure improvements such as sidewalks, shared use path, streetlighting, enclosed stormwater drainage system and relocation and/or upsizing of water and sewer lines.

Northwest Chipman Road between View High Drive and Northwest Bent Tree Drive will remain closed to through traffic for the project's duration. The project is expected to be completed in late spring 2025.

For more information, contact Public Works at publicworks@cityofls.net or 816.969.1800.

Print

Latest News

Alley Closure at 2nd Street for Gas Main Work

Alley Closure at 2nd Street for Gas Main Work

Alley Closure at 2nd Street for Gas Main Work

The alley at 2nd Street between SE Douglas and SE Green streets and next to the City Hall parking garage is closed daily from 7 a.m. to 5 p.m. for gas main replacement by a private utility contractor. There will be a lane shift on SE 2nd Street as well. Work is permitted through December 11.

Olive & Orchard Project Update: Road Closures for Stormwater Work Set for Week of Nov. 16

Olive & Orchard Project Update: Road Closures for Stormwater Work Set for Week of Nov. 16

Olive & Orchard Project Update: Road Closures for Stormwater Work Set for Week of Nov. 16
There are two upcoming road closures for stormwater work which are set to take place the week of November 16. NW Olive Street just north of NW Orchard Street is set to close Monday, November 16, through Tuesday, November 17. The detour route is intended to guide drivers from the south end of Olive over to Chipman and Douglas. NE Main Street just north of NW Orchard Street is set to close Wednesday, November 18, through Thursday, November 19.
Pryor Road Project Update - Hook Road Now Open

Pryor Road Project Update - Hook Road Now Open

Pryor Road Project Update - Hook Road Now Open

Hook Road at the Pryor Road intersection is now open in both directions between Horridge and Ward Roads.

Pryor Road to the south of Hook Road is now expected to open the week of November 16.

 

Snow Event Dry Run - City Crews Preparing for Winter Weather Season Today, Wednesday, November 4

Snow Event Dry Run - City Crews Preparing for Winter Weather Season Today, Wednesday, November 4

The City of Lee’s Summit is holding a snow event dry run from 7 a.m. to 3:30 p.m. today, Wednesday, November 4, to prepare for the upcoming 2026-2027 winter weather season. This exercise is an important part of the City’s annual preparation and helps ensure crews are ready to respond when winter weather arrives. City crews will be testing equipment and software, and driving snow routes with plows and salt spreaders installed on trucks. The purpose is...
1345Last