Green Street Project Update: SE Green Street Entrance into City Hall Now Open

The Southeast Green Street entrance into the Lee’s Summit City Hall parking lot and garage is now open.

Work on the Green Street project continues, and Southeast Third Street between Southeast Douglas Street and Southeast Grand Avenue remains closed to thru traffic.

Updates to estimated reopening dates are as follows:

  • Southeast Third Street from the alley by City Hall through the Southeast Green Street intersection is expected to open in early January 2025.
  • Southeast Third Street from Southeast Green Street through the Southeast Johnson Street intersection is expected to open in late February 2025.

All work is weather permitting and schedules are subject to change.

Print

Latest News

Ward Road Project Update - Blue Parkway Roundabout Set to Open

Ward Road Project Update - Blue Parkway Roundabout Set to Open

Ward Road Project Update - Blue Parkway Roundabout Set to Open

The new roundabout on Blue Parkway at Ward Road is set to open to eastbound and westbound traffic by the end of the day today, Friday, July 10.

Ward Road will remain closed to through traffic between Blue Parkway and O’Brien Road.

Section of NE Johnson Street between NE Maple Street and NE Short Street to Close Wed., July 1

Section of NE Johnson Street between NE Maple Street and NE Short Street to Close Wed., July 1

Section of NE Johnson Street between NE Maple Street and NE Short Street to Close Wed., July 1

A section of Northeast Johnson Street between NE Maple Street and NE Short Street is set to close to through traffic 9 a.m. to 4 p.m. on Wednesday, July 1, for approximately one week. The detour route includes Northeast Short Street, Northeast Green Street, and Northeast Maple Street. 