Upcoming Traffic Changes for the Green Street Project

Upcoming Traffic Changes for the Green Street Project

The Southeast Green Street entrance into the Lee’s Summit City Hall parking lot and garage is expected to reopen this afternoon Thursday, Sept. 26, and will remain open through the weekend for the Oktoberfest event. The Southeast Green Street entrance will close again on Monday, Sept. 30, and access to the City Hall parking lot and garage will once again be from the alley off of Southeast Second Street until approximately the end of November.

Also beginning Monday, Sept. 30, a traffic shift will be in place for eastbound traffic on Southeast Second Street from Southeast Green Street to Southeast Grand Avenue.

Looking ahead, a complete closure of Southeast Second Street from Southeast Green Street to Southeast Grand Avenue is anticipated Oct. 7-18. The detour route includes Southeast Grand Avenue, Southeast Third Street, and Southeast Douglas Street. A separate notification will be sent out regarding this closure.

All work is associated with the Green Street project. Schedules are weather permitting and subject to change.

 

Print

Latest News

Olive & Orchard Project Update: Road Closures for Stormwater Work Set for Week of Nov. 16

Olive & Orchard Project Update: Road Closures for Stormwater Work Set for Week of Nov. 16

Olive & Orchard Project Update: Road Closures for Stormwater Work Set for Week of Nov. 16
There are two upcoming road closures for stormwater work which are set to take place the week of November 16. NW Olive Street just north of NW Orchard Street is set to close Monday, November 16, through Tuesday, November 17. The detour route is intended to guide drivers from the south end of Olive over to Chipman and Douglas. NE Main Street just north of NW Orchard Street is set to close Wednesday, November 18, through Thursday, November 19.
Pryor Road Project Update - Hook Road Now Open

Pryor Road Project Update - Hook Road Now Open

Pryor Road Project Update - Hook Road Now Open

Hook Road at the Pryor Road intersection is now open in both directions between Horridge and Ward Roads.

Pryor Road to the south of Hook Road is now expected to open the week of November 16.

 

Snow Event Dry Run - City Crews Preparing for Winter Weather Season Today, Wednesday, November 4

Snow Event Dry Run - City Crews Preparing for Winter Weather Season Today, Wednesday, November 4

The City of Lee’s Summit is holding a snow event dry run from 7 a.m. to 3:30 p.m. today, Wednesday, November 4, to prepare for the upcoming 2026-2027 winter weather season. This exercise is an important part of the City’s annual preparation and helps ensure crews are ready to respond when winter weather arrives. City crews will be testing equipment and software, and driving snow routes with plows and salt spreaders installed on trucks. The purpose is...
Pryor Road Project Update - Intersection of River Run Drive and Pryor Road Set to Close Week of October 26

Pryor Road Project Update - Intersection of River Run Drive and Pryor Road Set to Close Week of October 26

Pryor Road Project Update - Intersection of River Run Drive and Pryor Road Set to Close Week of October 26

Update: This closure is likely to occur in the afternoon on Tuesday, Oct. 27.
The intersection of SW River Run Drive and SW Pryor Road is expected to close during the week of Oct. 26, until approximately the end of November. During this closure, school traffic will temporarily use the new SW 26th Terrace connection east of SW Pryor Road to access SW River Run Drive and the school.