Capital Project Status

Search Projects

Status: In Design   |   Estimated Construction: 4/3/2023 - 6/1/2024   |  
Categories: Bridges, Streets & Signals   |  

Chipman Road - View High Dr to Bent Tree Dr

Project Description:
This project is one of six projects funded by the 2007 1/2 cent sales tax renewal. This project will reconstruct the roadway as a 3-lane facility with turn lanes. The existing one-lane RR tunnel will be removed, and widened to support two-way traffic. A pedestrian bridge will be put in it's place.

Project Rationale:
SAFETY: This project will improve safety by leveling the roadway and improving sight distance. The right of way component will preserve right of way for future capacity improvements.

Current Project Status:
Utility relocations to start soon.  Major gas line relocation required by Spire.  Finishing Right of Way acquisition.  Roadway construction to start spring of 2023.  

Project Contact:
Craig Kohler 816-969-1800

Projected Funding: $17,280,000