Status: In Design   |   Estimated Construction: 9/1/2025 - 11/6/2026   |  
Categories: Bridges, Streets & Signals   |  

Pryor Road (Phase 2) - M150 Hwy to Hook Rd

Project Description:

This project is the second of two phases to complete committed improvements to Pryor Road from M-150 Highway to Longview Road. This second phase of the project will widen Pryor Road as a four-lane facility with turn lanes, sidewalk, shared-use path, curb, and street lighting from M-150 Highway to Hook Road.

Project Rationale:

This project supports improved safety, operations, community growth in southwest Lee’s Summit, and livability. The project is identified in the Thoroughfare Master Plan. The path is also included in the Greenway Master Plan and Bicycle Transportation Plan. Increased traffic demand and use by cyclists and pedestrians along this corridor will cause capacity issues and impediment to development nearby.  

Current Project Status:
Affinis selected as engineering consultant.  Survey is complete. Working on Preliminary design.

Project Contact:
Nikia Chapman-Freiberger 816-969-1800

Projected Funding: $10,450,000