Capital Project Status

Search Projects

Status: In Design   |   Estimated Construction: 2/3/2025 - 11/7/2025   |  
Categories: Storm Water   |  

Stormwater - SE Todd George Pkwy and SE 3rd St

Project Description:
Final design of engineering improvements to the stormwater system in the area of SE Todd George Pkwy and 3rd St.

Project Rationale:
Mitigate structural flooding in several locations within the watershed.

Current Project Status:  Allgeier Martin is the design consultant.  Regional detentions ponds are be looked at as part of the design.  Working on easement acquisitions.

Karen Quackenbush 816-969-1800