Third Street Improvements Updates

Find information about active road restrictions, closures and detours related to the Third Street Improvements Project. Questions about the private utility relocations or the Third Street Improvements Project can be directed to Public Works via email or 816.969.1800.

Learn More About the Third Street Improvements Project

General Project Updates

August 11, 2025

The contractor is completing Phase 1 with concrete paving on the north side of 3rd Street from Madison to Blue Parkway. Next will be installation of storm sewer and water mains in Phase 2 on the south side of 3rd Street from Madison to Walnut. Grading for paving for the eastbound lanes will follow. The contractor is making good progress in delivering the project on time. 

June 9, 2025

The first phase of the project has begun. Grading, storm sewer, watermain and base rock from Madison to Walnut Streets. Concrete paving to begin early June. Utility conflict challenges are only slowing progress, not stopping progress. The contractor is making good progress overall and on track to complete the project on time. 

May 9, 2025
The first phase of the project has begun and Jefferson Street has reopened to traffic. All traffic is eastbound only on the existing eastbound lanes. Utility conflict challenges are only slowing progress, not stopping progress. The contractor is making good progress overall and is on track to complete the project on time. 

March 10, 2025
The first phase of the project has begun. Closure of Third Street at Jefferson for watermain relocation is in place. Total closure of the first phase is 50 days. 

February 12, 2025
The intersection closure is postponed until Monday, February 24, due to the forecast for snow and subfreezing temperatures the week of February 17.

February 7, 2025
The intersection closure is postponed until Monday, February 17, due to the forecast for snow and subfreezing temperatures the week of February 10.

February 4, 2025
Construction on the Third Street Improvements project is officially set to begin on Feb. 10 and will last until November. The intersection of Southwest Third and Southwest Jefferson streets is set to close on Monday, Feb.10, for water main work and intersection improvements. The intersection will remain closed until early April. Work is weather permitting and schedules are subject to change.

Utility relocations for Spire, Google, Spectrum and AT&T are ongoing. There will be traffic control set up for both the utility relocations along the corridor and the construction work in the intersection.

 

Eastbound Only Traffic on Southwest Third Street

Eastbound Southwest Third Street Open; Westbound Southwest Third Street Closed

All eastbound traffic on Southwest Third Street is shifted to the north between Southwest Blue Parkway and Southwest Jefferson Street. Southwest Noel Street north of Southwest Third Street is now open.

Southwest Third Street between Southwest Blue Parkway and Southwest Jefferson Street remains closed to westbound traffic.

Eastbound Only Traffic on Southwest Third Street