Status: Future | Estimated Construction: 8/1/2024 - 9/1/2026 |
Indoor Sports Complex/Fieldhouse
Description:
In August 2016, Lee's Summit voters approved a continuation of the 1/4 cent sales tax for parks capital projects through 2033. One of the projects identified in the capital campaign was construction of an indoor fieldhouse for competitive and recreational sports and year-round training. Construction of a fieldhouse would be approximately 120,000 square feet. Final location to be determined.
Project Purpose:
Project is necessary to serve demands of growing youth sports associations in Lee’s Summit and for year round training and practice.
Estimated Schedule:
Design: June 2025-April 2026
Construction: May 2026-October 2027
Funding Sources:
Park Sales Tax FY25: $950,000
Park Sales Tax FY26: $9,450,000
Park Sales Tax FY25: $13,600,000
Total Lifetime Budget: $24,000,000
Estimated Annual Operating and Maintenance: $250,000