Status: In Design | Estimated Construction: 7/1/2022 - 6/30/2023 |
Eagle Creek/Park West Development
Project Description:
In August 2016, Lee's Summit voters approved a continuation of the 1/4 cent sales tax for parks capital projects through 2033. The project consists of construction of 1.75 mi of trail east and west of the Eagle Creek Park trail, development of neighborhood park space on the east side of the Park West property, and prepare a park master plan for the future use of 50 acre Park West property.
Project Purpose:
To provide additional trail and park amenities along Mouse Creek stream corridor for southern portion of Lee’s Summit. Trail would connect from Sampson Road through Park West and Eagle Creek Park and east to Pryor Road.
Estimated Schedule:
Planning and Design: July 2022 - October 2022
Construction: October 2022 - June 2023
Funding Sources:
Parks Sales Tax FY23: $200,000
Parks Sales Tax FY24: $850,000
Total Lifetime Budget: $1,050,000
Estimated Annual Operating and Maintenance: $10,000