3rd Street, Jefferson to Blue Parkway Status: In Design | Estimated Construction: 3/1/2023 - 11/1/2023 | Categories: Bridges, Streets & Signals | Updated: 06/23/2022 This project will improve 3rd Street from Jefferson Street to Blue Parkway. The project includes, but is not limited to, paving, sidewalks, curb and storm sewer work, street lighting and access management. The project may include additional streetscape elements along 3rd Street similar to those within the downtown central business district; and could provide those same elements such as brick pavers, landscape/street trees, etc. along portions of Market Street and...
Browning Street Extension - Browning Street to Hamblen Road Status: In Design | Estimated Construction: 8/22/2022 - 3/20/2023 | Categories: Bridges, Streets & Signals | Updated: 06/23/2022 This project will extend the current Browning street to connect with Hamblen Road. The project will include sidewalks, curb and gutter and turn lanes.
Chipman Road - View High Dr to Bent Tree Dr Status: In Design | Estimated Construction: 4/3/2023 - 6/1/2024 | Categories: Bridges, Streets & Signals | Updated: 06/23/2022 This project is one of six projects funded by the 2007 1/2 cent sales tax renewal. This project will reconstruct the roadway as a 3-lane facility with turn lanes. The existing one-lane RR tunnel will be removed, and widened to support two-way traffic. A pedestrian bridge will be put in it's place.
Colbern Road Status: In Design | Estimated Construction: 4/3/2023 - 9/1/2024 | Categories: Bridges, Streets & Signals | Updated: 06/23/2022 This project will widen Colbern Road as a four lane facility with turn lanes, sidewalk, shared-use path, curb, and street lighting from M350 Highway to Douglas Street. Project improvements include bridge work for bicycle/pedestrian accommodations over the UPRR. The shared-use path will be extended to the existing path along Colbern Road east and west of the project limits.
Douglas Street - Chipman Road to 2nd Street Status: In Design | Estimated Construction: 3/3/2025 - 12/31/2025 | Categories: Bridges, Streets & Signals | Updated: 07/01/2022 This project will improve Douglas Street from 2nd Street to Chipman Road. The project includes, but is not limited to, paving, sidewalks, curb, storm drainage work, street lighting.
Independence and Town Centre Intersection Improvements Status: In Design | Estimated Construction: 3/1/2023 - 8/30/2023 | Categories: Bridges, Streets & Signals | Updated: 06/23/2022 This project involves intersection reconfiguration at Independence Avenue and Town Centre Blvd, which is intended to direct thru-traffic along Town Centre Blvd rather than along Independence, to and from Colbern Road. A complimentary project is the installation of a traffic signal at Colbern and Town Centre along with turn lanes and a raised median on Colbern. The raised median will limit access to Independence from Colbern.
M291 North Interchange with US50 Status: In Design | Estimated Construction: 8/7/2023 - 12/1/2024 | Categories: Bridges, Streets & Signals | Updated: 06/23/2022 This project is the reconstruction of the interchange at M291 North Junction and 50 Highway, including relocation of the north outer road (Blue Parkway), improvements to 7th Terrace and work along US 50 Highway. This project will be competed in a partnership with MoDOT among other entities.
NW Main Street Status: In Construction | Estimated Construction: 3/1/2022 - 9/1/2022 | Categories: Bridges, Streets & Signals | Updated: 06/23/2022 Improve NW Main from Commerce to Chipman to full build-out of the commercial collector.
Pryor Road - Hook Rd to Longview Rd Status: In Design | Estimated Construction: 5/1/2024 - 10/31/2025 | Categories: Bridges, Streets & Signals | Updated: 08/08/2022 This project is the first of two phases to complete committed improvements to Pryor Road from M-150 Highway to Longview Road. This first phase project will widen Pryor Road as a four lane facility with turn lanes, sidewalk, shared-use path, curb, and street lighting from Hook Road to Longview Road. The project will also include permanent traffic signal installations at the Hook Road and Scherer Road intersections along Pryor Road, with interconnect to the traffic...
Ward Road & Persels Road Intersection Improvements Status: In Design | Estimated Construction: 5/1/2023 - 12/31/2023 | Categories: Bridges, Streets & Signals | Updated: 06/23/2022 This project is the installation of a permanent traffic signal to replace the temporary span wire traffic signal at the intersection of Ward Road and Persels Road. The project will include relocation of Persels Road, north intersection at Ward Road, to align with Persels Road, south intersection at Ward Road; addressing the operational and safety issues related to the existing offset intersections. The project will also include left-turn lanes along Ward Road at...