Capital Project Status

Search Projects

Status: In Construction   |   Estimated Construction: 10/5/2020 - 12/1/2021   |  
Categories: Storm Water   |  

12 Stormwater Projects

Project Description:
Projects indentified as part of 2007 bond issue. Projects have been award to 4 engineering firms. Designs expected to take 1 to 2 years based on complexity of projects with construction through 2021.

Project Rationale:
Projects to mitigate structure flooding.

Current Project Status:
Construction in the 700 block of SW 34th Street is complete.  Contractor went out business.  A second contractor is on board to finish area of SW Pinnell Circle and SW 2nd Street.  Most of the remaining work is grading and sodding.  Work will commence closer to September when it is best to lay sod. 

Construction completed in the 300 block of SE Bingham Dr, 100 block of NE Maple St, 400 block of SE Grand Ave, and 100/200 blocks of SE Brentwood Dr.   

Projects that started construction in June, 2021, include SW Lea Dr at Ward Road and NE Delta School Road at NE Port Dr.  Ward Road construction is to replace undersized box culverts.  2/3 of the box culvert has been replaced at this time and temporary two traffic, one lane each way has been put in place for a few weeks.  The west end of the box culvert will start replacement once a 24" water main has been moved.  

SE Hackamore storm pipe upsizing and Secretariat floodproofing still under design. 

Delta School Road is still under construction to replace numerous storm pipes and structures.

Project Contact:
Karen Quackenbush 816-969-1800