Commercial Permit Process

A commercial building permit is required for the construction, expansion, alteration or repair of any structure used for commercial purposes. This could be anything from the construction of a new office or retail facility to adding a wall or even a couple of outlets in an existing tenant space. The commercial permit process also covers the conversion of an existing structure previously used as a residence into a commercial use such as an office. Work that would not require the issuance of a permit are projects such as painting, floor coverings and replacement of fixtures where no plumbing or electrical work is being performed.

Building Permit Application

All commercial permits have the same basic requirements for application whether the project is the construction of a new building, a new commercial tenant space or the alteration of an existing space. The required documents for application are

Some projects will require a final development plan application be made to the Planning and Development Department. These projects are generally for a new building or an addition to an existing building. The building permit application cannot be processed until the final development plan application has been received by the Planning and Development Department.

Establishments which either sell or serve food are required to submit a separate permit application to the Jackson County Department of Public Works as they currently serve as the health officer for the City of Lee’s Summit. The health officer must approve the project plans prior to issuance of a building permit by the City of Lee’s Summit. Contact the Department of Public Works at 816-881-4530 for additional information. A separate set of project documents and plans shall be submitted directly to the Jackson County Department of Public Works for review and approval.


Plan Review Process

Once submittals are turned into the City, plans will be distributed to a Codes Administration plans examiner and the Fire Department for review. Comments from the review will be forwarded by Codes Administration to the design professional who prepared the drawings. The goal of the Codes Administration and Fire department staff is to complete review of new structures and additions to existing structures within ten (10) working days. The goal for all other permit applications is seven (7) working days.

Upon review of the comments, the design professional must make any requested changes and re-submit the necessary re-submittals to Codes Administration. The resubmitted information will then be distributed for review. The goal is to review all re-submittals within 5 working days. If all of the issues from the original comment list are resolved, the plans will be approved. Otherwise, another comment list will be sent to the design professional showing issues that still need resolved.

The Codes Administration staff will notify the applicant once the permit has been approved and is ready to be issued. If the project requires a final development plan application and review by the Planning and Development Department, the building permit will not be issued until that application has been approved. Likewise, if the project requires review and approval of the Jackson County Health Department, the permit cannot be issued until the Jackson County Health Department has approved the project.


Permit Fees

All fees associated with the building permit are collected at the time of permit issuance. Our police is to issue one permit to the person or company responsiblefor the overall completion of the project. The permit would cover all phases of the construction of the project and any related private services. The City of Lee’s Summit does not charge separate application or plan review fee for commercial building permits. For detailed information regarding the calculation and payment of building permit fees, please go to the Building Permit section of Development fees.

For an accurate estimate of the building permit fee for a project, please contact Codes Administration at (816) 969-1200 or go to the Contact Us page and choose “Codes Administration” as the department to contact.


Plan Review Expiration

An application for a permit for any proposed work shall be deemed to have been abandoned 180 days after the date of filing unless such application has been pursued in good faith or a permit has been issued. The building official is authorized to grant one or more extensions of time for additional periods not exceeding 90 days each. The extension shall be requested in writing and justifiable cause demonstrated.


Permit Expiration

Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. The building official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each. Failure to complete a project in the time limits or failure to maintain a valid permit constitutes a violation of the code. Refer to Section 7-134 of the Lee's Summit Code of Ordinances for additional information.